Configuration of gauge
THE ENERGY METER
The energy meter needs to be configured on mains voltage, I will describe the procedure now, even though it was performed later after the safety inspection. The configuration was carried out as follows:- The language was set to German.
- Network settings were adjusted, including assigning a static IP address and setting the subnet mask.
- The network type was set to: 3PH-4W-3CT, indicating a 3-phase network with four conductors and three current transformers.
- The current transformers were configured, specifying a ratio of 50 A primary current to 5 A secondary current.
- Finally, the configuration was verified and approved. The meter has a "0100" pin for saving changes.
The current transformers are mounted on a DIN rail inside of the controll cabinet. For that purpose we printed holders with 3D printers as shown in picture 2 and 3.
Figure: The energy meter
Figure: holder for the current transformers
Figure: mounted current transforms on the holder
Last modified: Monday, 3 July 2023, 5:32 PM